Amkor Anam Philippines, Inc. (AAPI) is a semiconductor company engaged in assembling electronic components. To expand their P1 Facility operation, they decided to convert two (2) old warehouse buildings with a combined area of 6,000 square meters into a 12,000square meter assembly/test facility. They doubled the total area of the said facility by adding a second floor.
A two-storey structure was added in front in order to house a lobby and some toilet facilities. Another structure was built at the back to serve as the housing of the power substation, chillers, and even more toilets. Subsequently, a two-storey annex was constructed along one side of the facility to serve as offices and the central lockers area.
RNFA provided total engineering and structural design services for the entire project and, in addition, the firm managed the construction for the central lockers annex and handled production fit-up. The success of this engagement led to more renovation, facility conversion and expansion projects for RNFA within the AAPI’s P1 Facility Compound.
PROJECT FACTS
Project Name AAPI AREA 5 FACILITY
Location NSC Compound KM 22 East Service Road, South Superhighway, Muntinlupa, Metro Manila, Philippines
Owner/Client AMKOR ANAM PHILIPPINES, INC.
Type of Facility Semiconductor Plant
Floor Area (m2) 36,000
Project Value US $ 12 M
RNFA Scope of Work Architectural/Engineering Design & Project Management Services
Date CompletedJune 1995