Primarily due to an expansion in their output, Hadsys Philippines Corporation, a sister company of Honda Philippines, decided to move out of Phase I of LTI and put up their own plant at Phase IV of the LTI Sta. Rosa, Laguna. This new warehouse type plant was built to handle the production on the air-intake manifold and the assembly of the air condtioning units for local vehicles as well as for export purposes.

The plant site is approximately 25,000 square meters. On the other hand, the building floor area covers 4,623 square meters. The building itself is divided into two major sections, namely: the production area (3,522 square meters) and the office area (1,101 square meters).

RNFA’s services for this project started from design conceptualization all the way up to the actual construction management. From the start of rough grading work up to the completion of the facility, the construction period took 11 months.

PROJECT FACTS

Project Name HADSYS PLANT

Location Laguna Technopark, Inc. (LTI), Sta. Rosa Laguna

Owner/Client HADSYS Philippines Corporation

Type of FacilityManufacturing Plant

Floor Area (m2) 25,000

Project Value US $ 1.57 M

RNFA Scope of Work Architectural/Engineering Design & Project Management Services

Date Completed April 1999

 